Home (re) Insurance Latin America Allianz: The 7 trends making engineering and construction projects bigger and costlier than ever

Allianz: The 7 trends making engineering and construction projects bigger and costlier than ever

11 min read
  • Flooding of the Hidroituango hydropower dam in Colombia in 2018 during construction is estimated to cost insurers around $1.4bn, one of the largest engineering claims in history.
  • Projects are increasingly complex, often with values in the tens of billions of dollars, and can run for decades.
  • Fire and explosion incidents most expensive losses globally. Defective product and business interruption claims rising. Trade disputes growing concern.
  • New tech such as drones, satellite imagery and laser scanning helping to better identify risks, cause of loss, and speed up claims.

Large engineering and construction projects have changed beyond recognition in recent decades. Whether it is an airport, a power plant or a car manufacturing complex, sites are now much larger, more complex and more expensive, meaning more is at stake if things go wrong.

Analysis by Allianz Global Corporate & Specialty (AGCS) of more than 13,000 engineering insurance claims over the last five years has identified seven major trends in engineering and construction projects, driving some of the largest losses ever, according to a new report by the insurer. The report also examines how new technologies, such as drones, satellites, lasers, and computer modeling, are increasingly being used to speed up claims and mitigate risks:

Construction sites today are much larger than in the past and projects can run for many years. The expansion of the Al Maktoum International Airport in Dubai, for example, will not be completed until 2030 and is expected to cost around US$36bn. “As a result, sums insured are now much larger – projects with values of $5bn to $10bn are not unusual, meaning claims can be in the tens of millions of dollars,” says Raymond Hogendoorn, Global Head of Property and Engineering Claims at AGCS.  Flooding of the Hidroituango hydropower dam in Colombia in 2018 during construction is estimated to cost insurers around $1.4bn, one of the largest engineering claims in history.

Fire is the biggest cause of loss for engineering claims, accounting for over a quarter (27%) of losses by value, based on analysis of more than 13,000 claims around the world worth almost €8bn ($8.8bn). Fire has caused in excess of €2.1bn ($2.35bn) of insurance losses in five years. Natural catastrophes are another source of large claims. For example, storm damage is the second biggest cause of loss by number, accounting for one in 10 claims. Natural catastrophes also rank as the top concern for construction firms in the Allianz Risk Barometer 2019 [1].

Defective products are the single biggest source of engineering claims by frequency, and the second largest by severity, according to AGCS claims analysis. There are almost three times as many defective products claims as storm claims, the next largest cause of claims by frequency. “We are seeing an increase in claims related to defects and quality control across the board,” says Martin Eckel, Senior General Adjuster at AGCS. For example, two major power generation claims — $200mn events — were caused by defective welding.

 

In the past, an airport or a power plant would most likely have been built by a national contractor using local suppliers. Today, it is more likely to involve multiple parties with machinery, equipment and other components sourced and transported from around the world. “Technology is becoming more sophisticated and specialized, which can increase the costs to repair or replace machinery and equipment. If a turbine coming from China is damaged in transport, it might take as long as 18 months for a repair,” says Eckel.

Construction and engineering firms ranked business interruption (BI) as the second most concerning risk in the Allianz Risk Barometer 2019. Growing awareness of BI exposures has seen an increase in firms buying BI covers, in particular delay in start-up (DSU) insurance, which covers delays to construction or engineering projects following physical damage. DSU claims are usually expensive – indemnity for delay in start-up has increased over time from around $200,000 per day to up to $500,000 per day.

Lowers Forensics International - A complete Solution For Latin America

Large construction projects can take as long as five to 10 years to complete and involve contractors and suppliers from around the world, making them vulnerable to sanctions and trade disputes. For example, sudden and large increases in US import tariffs can add millions of dollars to claims for plant equipment and machinery imported from countries such as China.

As the demand for green energy has increased, solar and wind projects have become larger, the locations more remote and wind turbines much bigger – with blades as long as a football pitch. In 2018 alone, there were 409 new offshore wind turbines across 18 projects in the EU. Offshore wind can be a particularly challenging area for claims, as turbines can be difficult to access.

As large engineering and construction projects have become more complex, assessing risks and claims and establishing the ultimate cause of loss has become much more difficult. However, insurers have an increasing array of new technology at their disposal to offer support:

  • AGCS recently utilized drones, laser scanning, and computer modeling to determine the root cause of a machinery explosion at an inaccessible site. Drones and satellite imagery were also used to assess engineering claims after record wildfires in California and Hurricane Florence in 2018.
  • AGCS is coupling 3D topographical data from drones with hydrogeological modeling software and rainfall simulation data to predict flash flooding risk on construction sites.
  • Satellite technology offers high resolution images of a site within 24 hours of a loss, even at remote or hazardous locations. It can also be used to combat exaggerated or fraudulent claims.

“Technology will create more certainty for engineering claims,” says Hogendoorn. “There are so many parties on a site at one time, and so many activities happening simultaneously, it can be extremely difficult to understand the sequence of a loss event. However, we can increasingly use technology to access data and information to better understand the root cause of loss and speed up the claims process.”

[1] The Allianz Risk Barometer surveys more than 2,400 global risk experts about the major threats to their business.

Source: Allianz

About iNLIP

Load More Related Articles
Load More By iNLIP
Load More In (re) Insurance Latin America

Check Also

Last seats available! 2024 Insuralex Miami International Insurance Summit

We are proud to announce that almost 90% of the seats are already reserved. Once all seats…